Ventilation Ductwork System for Biopharmaceutical Cleanrooms

June 16, 2025
Latest company case about Ventilation Ductwork System for Biopharmaceutical Cleanrooms
Comprehensive Technical Specifications for Design and Installation
1. Interstitial Duct Colored Insulation System
l Use flame-retardant PIR/PUR foam insulation with density ≥48kg/m³ and thermal conductivity ≤0.022W/(m·K)
l Insulation thickness designed per process requirements, typically 25-40mm, with colored PVC protective layer
l Ensure specialized tape sealing at joints with smooth, wrinkle-free surface
latest company case about Ventilation Ductwork System for Biopharmaceutical Cleanrooms  0
2. Return Air Riser Installation
l Use 304 stainless steel rectangular ducts with wall thickness ≥1.2mm
l Vertical deviation ≤2mm/m, total length deviation ≤10mm
l Support spacing ≤3m with rubber vibration isolators
latest company case about Ventilation Ductwork System for Biopharmaceutical Cleanrooms  1
3. High-Efficiency Air Outlet Edge Banding
l Use anodized aluminum trim with thickness ≥2mm
l Apply medical-grade silicone sealant at joints, 3-5mm bead width
l Install EPDM gasket at color steel panel connections
latest company case about Ventilation Ductwork System for Biopharmaceutical Cleanrooms  2
4. Stainless Steel Air Outlet Installation Standards
l Select 316L medical-grade stainless steel with electropolished surface
l Pre-installation laser leveling with deviation ≤1.5mm/m
l Use quick-release flange connections at duct joints
latest company case about Ventilation Ductwork System for Biopharmaceutical Cleanrooms  3
5. Duct Wall Penetration Sealing System
l Provide sleeves 50mm larger than duct diameter, filled with fireproof rockwool
l Seal both sides with fire-resistant putty, thickness ≥30mm
l Install stainless steel finishing rings
latest company case about Ventilation Ductwork System for Biopharmaceutical Cleanrooms  4
6. Exhaust Fan Grounding Specifications
l Use 6mm² yellow-green copper wire for grounding
l Apply OT terminal crimping with anti-loosening washers
l Quarterly grounding resistance testing with documented records
latest company case about Ventilation Ductwork System for Biopharmaceutical Cleanrooms  5
7. Integrated Ceiling BIM Coordination
l Conduct clash detection using Revit+Navisworks
l Maintain ≥600mm access clearance with ≥300mm equipment spacing
l Provide 3D isometric drawings for construction guidance
latest company case about Ventilation Ductwork System for Biopharmaceutical Cleanrooms  6
8. Crossover Walkway Technical Requirements
l Main structure using hot-dip galvanized steel with ≥85μm zinc coating
l Tread plates made of 304 stainless steel grating with ≤20mm openings
l Install double-rail guardrails with intermediate wire rope protection
latest company case about Ventilation Ductwork System for Biopharmaceutical Cleanrooms  7
9. Supplementary Technical Specifications
l All ducts require PAO leak testing
l System noise control at ≤65dB(A)
l Final air balance report required upon completion
 